The installation of the solar power plant in Konya-Karapınar was completed and commissioned
on 01.03.2023 with an installed capacity of 1,350 MWp/1,000 MWe. This facility generates at
least 2 billion kWh of electricity per year.
With the YEKA SPP-3 Competitions held in 2021, it was aimed to allocate a total of 1,000 MWe
connection capacities of 10 MWe, 15 MWe and 20 MWe each, covering 36 provinces, to 74 diffe-
rent investors, and the YEKAs to be announced on the condition of using photovoltaic modules
with at least 70% domestic contribution rate. Environmental Impact Assessment (EIA) proces-
ses are ongoing for the projects.
Within the scope of YEKA SPP-4 Competitions held in 2022, competitions were held for the ins-
tallation of 15 solar power plants in 50-100 MWe capacities in Niğde-Bor, Hatay-Erzin and Şan-
lıurfa-Viranşehir YEKA in order to allocate a total of 1,000 MWe connection capacity with the
condition of using photovoltaic modules with at least 75% domestic contribution rate.
Map -6 Türkiye Wind Energy Potential Atlas (General Directorate of Energy Affairs (GDEA), 2024)
Wind Speed
(m/h)
The installation of the 25 MWe Akköy Wind Power Plant (WPP) Project in Aydın Region was
completed in 2023. EIA and zoning studies are ongoing for the remaining capacity.
th
Within the scope of the 12 Development Plan, energy sector targets for 2028 are given in Table
13.
Table -13 Energy Sector Targets for 2023 (12 Development Plan, 2024)
th
Targets Target Year: 2028
Primary Energy Demand (BTEP) 190,000
Electric Energy Demand (TWh) 430
Per Capita Primary Energy Consumption (TEP/Person) 2
Per Capita Electricity Consumption (kWh/Person) 4,700
Share of Natural Gas in Electricity Generation (%) 15
Share of Renewable Resources in Electricity Generation (%) 50
Amount of Electric Energy Generated from Domestic Sources (TWh) 270
Electricity Installed Capacity (MW) 136,000